What can purchasing send today?

Suppose a contractor needs 12 km of 24-fibre ADSS for a district build. The bill lists one cable line, an allowance for fittings and delivery to a regional depot. Send that revision now with quantities and units. Ask for a budget unit price against a named construction and record how long the offer is valid.

What changes once the drawing arrives?

Mark the longest crossing, route turns and terminations on the pole schedule. Include the design loading conditions. Ask the supplier to identify the cable and compatible hardware against that information. A quoted reel length helps plan deliveries. It cannot determine how many dead ends the route requires.

Give freight a destination

A price to a port and a price unloaded at an inland depot cover different work. Give the depot city, access restrictions and requested delivery term. When a second depot is added, revise the drum allocation and request a separate freight line.

A message you can send

“Please price the attached BOQ revision B. Cable quantity is provisional. Our pole schedule follows on Friday. Show your assumed cable design, hardware unit prices and freight to the named depot separately.” Put each pending item beside the person responsible for confirming it.

Illustrative BOQ worksheet

CheckWhat to record
24-fibre ADSS, 12 kmBudget per km against stated span and load assumptions
Dead-end setsUnit price pending approved cable and termination count
Suspension setsUnit price pending support schedule
DeliveryFreight subject to drum weights and depot address

What to record

  1. Budget per km against stated span and load assumptions
  2. Unit price pending approved cable and termination count
  3. Unit price pending support schedule
  4. Freight subject to drum weights and depot address